The stairs are carpeted

Views : 715
Update time : 2017-06-02 20:41:03
The fixed way of stair carpet
(1) the pressure bar is fixed
(2) the bond is fixed
(3) the article card

Two, the pressure pole fixed stair carpet laid
(1) bury the press fastener.
Each step has two fasteners for each step, and the centerline symmetry of the width of the staircase is set.
The wall of the fasteners is equal to the distance from the stair tread and the kick face, and slightly less than the thickness of the carpet.
(2) the length of the carpet should be cut by the amount of tread on each stage, the width of the kick and the amount of the actual width of the kick.
(3) carpet is laid down from top to bottom.
Carpet of top end use nail bead platform: step fasteners per level position, on the carpet cut small mouth, let compressive bar fasteners can stretch out, and then wear the metal rod into the fastener hole, tighten the adjustment screw.
(4) must be metal, prevent slippery stairs after the carpet is good, with the expansion screw (or plastic tube expanding) will prevent slippery metal fixed on the edge of the step plate Yang Angle, from 15 to 30 cm.

3) the laying of a fixed stair carpet
(1) cutting the carpet in full measure.
(2) all of them are full of glue.
(3) from top to bottom with plastic float binder to impress on the stair tread and play, after appropriate air buy the carpet glue, and then rolling pressure with flat shovel, make carpet rolling flat, compaction.
(4) it is not possible to scrape the rubber, to lay the layer by stage, to avoid the big pieces of rubber and then spread the carpet.
(5) if you have to install the metal sliders, the same pressure bar is fixed.
(6) no traffic is allowed in 24H after the post.

Four, the stair carpet laid by the stationary stair
(1) to pin the barbed board on the stair tread, and I kick the two sides of the corner between the two sides of the corner, and the two barbs are left in the 15MM space between the two barbs, and the upside of the barbed plate is inclined to the Yin Angle.
The carpet should cover the tread of the stairs, and cover the Angle of the sun, and the width should not be less than 15MM.
(3) the carpet should be made with the sum of the width of the kick and the width of the kick.
(4) the top floor of the carpet is nailed down on the platform and then laid down from top to bottom.
At each stage of the stage, the carpet will be tightened with a flat shovel and pressed into the gap between the two sides.
(5) the length of the reserved section is on the first step.